SR 315 to close north and south of SR 750 mid January

Monday, Jan. 23 –
State Route 315 – At 5 a.m., SR 315 south of SR 750 to Jewett Road will close for three weeks, weather permitting, for tree clearing and utility relocation. The detour is SR 750 to US 23 to I-270 to SR 315. Beginning January 19, the tree clearing will occur around the clock for three days or until January 21. Chippers, chainsaws, generators and lights will be used for this work. The work will be loud.

Completion: Tuesday, Feb. 14 at noon, weather permitting.

Monday, Jan. 30 – 

State Route 315At 5 a.m., SR 315 north of SR 750 to Retreat Lane will close for 3 ½ months or 100 days for construction of the stabilization wall. The detour is SR 750 to US 23 to SR 315 or reverse. Wall construction will occur during daytime hours only.

Completion: Monday, May 8, weather permitting.

Please note: During the SR 315 closures, SR 750 (both directions) will remain open.

For up-to-date traffic information, construction information and road conditions, 24-hours a day, visit www.Ohgo.com.